May 16, 2022
Hole dig done back tomorrow to put in steel and start building the pool
May 17, 2022
Not a fun day today the rain just would not go away still managed to push though and get the steel in had to postpone concrete to tomorrow
May 18, 2022
Plumbing all done time to get walls and floor ready and get this liner in today
Big Day again from a muddy hole to an amazing well prepared hole all shaped and liner is in water truck has dumped 16000 litres in the pool back tomorrow to finish filling up and do the concrete bond beam great effort this week from the whole team
May 19, 2022
Pool all filled up now to do the concrete bond beam
Concrete bond beam done this pool is up and running but we will be back once the coping is done to install a little water feature cant wait to see this one all finished its going to look really cool